TM 5-3820-276-10-1
0030
ROD HANDLING ARM SUPPORT BRACKET INSTALLATION - Continued
21.
Set LIFTING BEAM switch (Figure 13, Item 1) to DOWN position and lower lifting beam (Figure 13, Item 5)
to its lowest position.
2
1
2
3
7
4
6
5
WWDS00983
Figure 13. Rod Handling Arm.
22.
With aid of assistant, set and hold PIPE POSITIONING ARM ELEVATION switch (Figure 13, Item 7) to
LOWER position until automated rod handling arm (Figure 13, Item 2) is in full down position.
23.
With aid of assistant, set and hold CLAMP switch (Figure 13, Item 6) in up position to lock clamps
(Figure 13, Item 3) to support bracket (Figure 13, Item 4). Ensure clamp is secured to bracket.
24.
Perform post operation of WWDR, if required (WP 0029).
END OF TASK
END OF WORK PACKAGE
02/13/2013root(opusualwp)wpno(O10017)