Figure 11. Automated Rod Handling Arm in Down Position.
Figure 2. Drill Bit

Technical Manual For Water Well Drilling System (Wwds) - 1 Page Navigation
  323    324    325    326    327  328  329    330    331    332    333  
img
. . . .
TM 5-3820-276-10-1
0028
OPERATOR MAINTENANCE
DRILL BIT INSTALLATION AND REMOVAL - WATER WELL DRILLING RIG (WWDR)
INITIAL SETUP:
Tools and Special Tools
Materials/Parts (cont.)
Adapter, Sub
(Volume 2, WP 0233, Table 1, Item 2)
(Volume 2, WP 0231, Table 1, Item 64)
Brush, Dope
Personnel Required
(Volume 2, WP 0231, Table 1, Item 6)
Two
Hoisting Plug
(Volume 2, WP 0231, Table 1, Item 36)
Hoisting Plug
References
(Volume 2, WP 0231, Table 1, Item 70)
WP 0027
Sling, Nylon Web, 8-ft
(Volume 2, WP 0231, Table 1, Item 58)
Equipment Condition
WWDR setup with engine on (WP 0017)
Materials/Parts
Antiseize Compound
DRILL BIT INSTALLATION
WARNING
Always wear double hearing protection, safety glasses, hard hat, gloves, and steel toe
shoes during operation of the Water Well Drilling System. Failure to comply may result in
injury or death to personnel. Seek medical attention in the event of an injury.
1.
Install drill rod in tophead, if required (WP 0027).