GRAVITY BAR WELDMENT REPLACEMENT
Figure 4. Gravity Bar Weldment Installation.

Field Maintenance Manual Tools List For Engineer Mission Module - Water Distributor Page Navigation
  879    880    881    882    883  884  885    886    887    888    889  
img
.
TM 5-3825-270-23&P
0160
REMOVAL - Continued
4
5
Figure 2. Gravity Bar Weldment Removal.
3.
Remove two locknuts (Figure 3, Item 8), four washers (Figure 3, Item 7), two screws (Figure 2, Item 6), and
gravity bar weldment (Figure 3, Item 1) from power unit frame (Figure 3, Item 9). Discard locknuts.
6, 7, 8
6, 7, 8
1
9
Figure 3. Gravity Bar Weldment Removal.
END OF TASK
INSTALLATION
1.
Install gravity bar weldment (Figure 4, Item 1) on power unit frame (Figure 4, Item 9) with two screws (Figure
4, Item 6), four washers (Figure 4, Item 7), and two locknuts (Figure 4, Item 8).