PORTABLE WATER TANK SETUP AND POST OPERATION PROCEDURES
Figure 3. Portable Water Tank Post Operation

Technical Manual For Water Well Drilling System (Wwds) - 1 Page Navigation
  625    626    627    628    629  630  631    632    633    634    635  
img
.
TM 5-3820-276-10-1
0061
PORTABLE WATER TANK SETUP - Continued
2.
Spread liner (Figure 1, Item 2) as necessary.
END OF TASK
PORTABLE WATER TANK POST OPERATION
1.
Release buckle (Figure 2, Item 1) from liner (Figure 2, Item 2) and place drain (Figure 2, Item 3) on ground
to drain water from portable water tank (Figure 2, Item 4).
1
2
4
3
WWDS00647
Figure 2.
Portable Water Tank Drain.
2.
Connect buckle (Figure 2, Item 1) to liner (Figure 2, Item 2).
3.
Make sure portable water tank frame (Figure 3, Item 3), liner (Figure 3, Item 2), and rope
(Figure 3, Item 4) are not damaged prior to folding frame. If damage is found, notify maintenance.
0061-2