TM 5-3820-276-10-1
0023
DRILL ROD STORAGE CARTRIDGE LOADING - Continued
result in injury or death to personnel. Seek medical attention in the event of an
injury.
Never operate the crane with less than three wraps of cable on the winch drum to
prevent excessive load on the cable anchor clamp and to avoid a potential safety
hazard. Failure to comply may result in injury or death to personnel. Seek medical
attention in the event of an injury.
NOTE
Tooling joint must be positioned at front of cartridges.
12.
With aid of three assistants, use WWSV truck-mounted crane to install drill rod (Figure 4, Item 2) into drill
rod storage cartridge (Figure 4, Item 7) (WP 0034).
NOTE
Nylon web slings (tag lines) must be removed before lowering drill rod completely.
13.
Remove nylon web slings (tag lines) (Figure 4, Items 4 and 6) from drill rod (Figure 4, Item 2).
14.
Lower WWSV truck-mounted crane hook (Figure 4, Item 1) (WP 0034).
NOTE
Ensure drill rod is pushed forward before removing drill pipe casing sling.
15.
Remove drill pipe casing sling hooks (Figure 4, Items 3 and 8) from drill rod (Figure 4, Item 2).
16.
Set LIFTING BEAM switch (Figure 4, Item 11) to DOWN position and lower lifting beam (Figure 4, Item 5)
and drill rod (Figure 4, Item 2) enough for next drill rod to be placed into drill rod storage cartridge.
17.
Repeat Steps 8 through 16 until drill rod storage cartridge (Figure 4, Item 7) is full with maximum of eight
drill rods.
18.
Set LIFTING BEAM switch (Figure 4, Item 11) to DOWN position and lower lifting beam (Figure 4, Item 5) to
lowest position.
19.
Set and hold PIPE STORAGE CARTRIDGES INNER switch (Figure 4, Item 10) to left position to move drill
rod storage cartridge (Figure 4, Item 7) to inner position.
20.
Set and hold PIPE STORAGE CARTRIDGES OUTER switch (Figure 4, Item 9) to left position to move drill
rod storage cartridge (Figure 4, Item 7) over lifting beam (Figure 4, Item 5).
21.
Repeat Step 6 and Steps 8 through 16 until drill rod storage cartridge (Figure 4, Item 7) is full with maximum
of eight drill rods.
22.
Set LIFTING BEAM switch (Figure 4, Item 11) to DOWN position and lower lifting beam (Figure 4, Item 5) to
lowest position.
23.
Set and hold PIPE STORAGE CARTRIDGES OUTER switch (Figure 4, Item 9) to right position to move drill
rod storage cartridge (Figure 4, Item 7) to outer position.
24.
Repeat Step 6 and Steps 8 through 16 until drill rod storage cartridge (Figure 4, Item 7) is full with maximum
of nine drill rods.
25.
Remove drill pipe casing sling (Figure 4, Item 1) from WWSV truck mounted crane hook (Figure 4, Item 1).
0023-7
02/13/2013root(opusualwp)wpno(O10020)