TM 10-4930-236-13&P
ASSEMBLY
a.
Thread nuts (17) on adjusting bolts (3). Install fuse nuts (16) and adjusting bolts (3) in yokes (9).
Attach yokes to control levers (14 and 13) with roll pins (8).
b.
Install trip lever (15) in container (18) and insert shaft (11). Install spacer (12) and control levers (13
and 14) as shaft (11) is pushed into place. Make sure hole in shaft is alined with hole in container boss.
c.
Install spring pin (10).
INSTALLATION
a.
Position lever assembly (7) on A-Frame, aline holes and install screws (5) and lockwashers (6).
b.
Move levers (13 and 14) forward to OFF position.
c.
Insert cable (2) from front tank valve through bushing (4) on left side and install nut (1) on cable. Pull
cable taut and install in groove of adjusting bolt (3). Screw nut (1) onto adjusting bolt (3) tight enough that
cable (2) does not slip.
d.
Insert cable (2) from rear tank valve through right side bushing (4) and connect as above.
4-41