PREPARATION FOR OPERATION/ENGINE START-UP
INITIAL SETUP:
Not Applicable
PREPARATION FOR OPERATION/ENGINE START-UP
1.
Refer to (TM 9-2320-364-10) for Operation of PLS truck.
2.
Inspect water distributor for damage that may have occurred during transport.
3.
Check and tighten all fasteners, body tie-down bolts, pipe and circulating line connections, etc., that may have
loosened during transit.
4.
Fill water distributor with at least 300 gallons of water (WP 0011).
CAUTION
Do not let engine pump run more than 5 minutes without circulating water through pump.
Failure to comply may result in damage to equipment.
5.
END OF TASK
END OF WORK PACKAGE