Figure 7. WWDR Left Rear Outer Wheel and Tire Assembly Installation
Figure 9. WWDR Wheel and Tire Assembly Torque Sequence

Technical Manual For Water Well Drilling System (Wwds) - 2 Page Navigation
  542    543    544    545    546  547  548    549    550    551    552  
img
.
TM 5-3820-276-10-2
0206
WWDR REAR WHEEL AND TIRE ASSEMBLY REPLACEMENT - Continued
NOTE
There are 10 lug nuts. Socket shown on one lug nut.
27.
Install 33-mm socket (Figure 8, Item 2) and extension (Figure 8, Item 1) on lug nut (Figure 8, Item 3).
1
2
3
4
7
6
5
WWDS00887
Figure 8.
Torque Multiplier Installation.
28.
Install torque multiplier (Figure 8, Item 6) to extension (Figure 8, Item 1).
29.
Install extension bar (Figure 8, Item 7) to torque multiplier (Figure 8, Item 6).
NOTE
Torque multiplier has 3 to 1 gear ratio. Wheel torque is 480 lb-ft (651 Nm).
30.
Adjust torque wrench (Figure 8, Item 5) to 160 lb-ft (217 Nm).
31.
Install adapter (Figure 8, Item 4) to torque wrench (Figure 8, Item 5).
32.
Install torque wrench (Figure 8, Item 5) to torque multiplier (Figure 8, Item 6).