TM 5-3820-276-10-1
0049
MUD PUMP HOSE CONNECTIONS - Continued
4.
Pull safety cable wedge (Figure 11, Item 1) down to open loop in safety cable (Figure 11, Item 2).
1
2
3
4
WWDS00052
Figure 11. Mud Pump Connection (View 2).
5.
Install safety cable (Figure 11, Item 2) to 3-in. (76 mm) inlet (Figure 11, Item 3).
6.
Connect 3-in. (76 mm) hose (Figure 11, Item 4) to drilling rig inlet (Figure 11, Item 3).
7.
Fill the MCS water tank with water (WP 0036).
END OF TASK