TM 5-3820-276-10-1
0034
TRUCK MOUNTED CRANE OPERATING PROCEDURE - Continued
WARNING
Check the inspection date of all lifting devices. Never use lifting device that has an expired
inspection date. Failure to comply may result in injury or death to personnel. Seek medical
attention in the event of an injury.
NOTE
Truck mounted crane is now ready to attach a load as needed.
17.
Push winch up/down toggle switch (Figure 5, Item 5) to down position to give slack in cable and lower
snatch block (Figure 5, Item 2).
18.
Make sure to follow load capacity chart restrictions as shown in Figure 6.
0034-7