TM 10-4320-307-24
3-20
ENGINE ASSEMBLY REPLACE (CONT).
INSTALLATION:
1.
Install engine mounting brackets (1 and 2) to engine assembly (3).
2.
Install all other mounting brackets and accessories which were removed during engine removal procedure.
The engine lifting equipment must be designed to safely lift the equipment.
3.
Position a hoist having a minimum rating of 3500 lb (1590 kg), with the engine lifting fixture (4) over engine assembly
(3).
4.
Attach hooks of lifting fixture (4) to engine lifting brackets (5).
Death
or
serious
injury
could
occur
if
unauthorized or unnecessary personnel are in
the hoisting area. Permit only personnel
actually engaged in the hoisting operation to
be near the unit and hoisting equipment. All
instructions for the hoisting operations must
come from one authorized person.
Injury to personnel or damage to equipment
could occur from improper hoisting. Hoist the
load slowly to avoid tearing out lifting
brackets. Do not jerk the load or swing it from
side-to-side when hoisting. This places
additional stress on hoisting components
which can cause failure and loss of load. Be
sure hoisting equipment is on solid footing.
Watch boom angle and overhead clearance
when hoisting.
5.
Lift engine assembly over skid (6) and position engine
mounting brackets (1 and 2) over mounting areas on skid.
6.
Gently lower engine assembly (3) onto skid (6),
retaining slight tension on hoist to allow engine
movement to align mounting holes.
3-51