TM 10-4630-206-12&P
0005 00
OPERATING PROCEDURES
To operate the SEP, ensure that all necessary hose connections have been made, and are secure.
Unused inlet ports must be capped. The drain valve, if present, must be closed. Ensure the SEP is
safely and securely connected to the power supply.
Operation (9-1-0150-1 and 9-1-0150-2)
1. Open breaker box door.
2. Release lid fasteners, and remove lid.
3. Turn SEP main circuit breaker (1) to ON.
WARNING
Ensure that the SEP has been thoroughly cleaned with chlorine
solution and rinsed prior to any inspection or service to the interior.
Failure to do so may result in serious illness or death to personnel.
4. Set float switch activation height by adjusting the height of the float switch cord retainer (2) on the
PVC retainer bar (3).
5. Turn pump circuit breaker (4) to ON.
6. Monitor initial operation of pump (5). If sewage does not evacuate, turn the pump on and off several
times to eliminate possible air lock.
7. In ambient temperature of 32 F or below, turn tank heater circuit breaker (6) to ON.
8. Although SEP operation is automatic, frequently check its proper functioning to avoid problems that
may arise due to prolonged operation.
3
6
2
4
1
5
0005 00-5