TM 10-4320-307-24
2-33
NETWORK CABLE TEST/REPLACE.
This task covers:
a. Removal
b. Testing
c. Installation
INITIAL SETUP
Test Equipment
Equipment
Multimeter (Item 12, Appendix B)
Condition
Tools
Reference
Condition Description
Paragraph
Field instrument layout removed
Tool kit, general mechanic's (Item 1, Appendix B)
2-30
Materials/Parts
Paragraph
Conduit layout removed
Nylon straps
2-31
Paragraph
Junction box removed
2-32
Paragraph
Wiring, gages, switches, and
2-28
indicators removed
Paragraph
Battery cables disconnected
2-27
Engine shut down and cool
General Safety Instructions
Well ventilated area
REMOVAL:
CAUTION
Use care not to damage the underlying cables or wires when removing nylon straps.
Removal of the network cables consists of cutting the nylon straps securing the cables being removed. Use diagonal
pliers to reduce damage to underlying cables or wires.
TESTING:
Test wires and cables for continuity and inspect for broken, burred, damaged, or frayed wiring. Replace cables as
required. Notify direct support maintenance if repairs to cables are required.
INSTALLATION:
1.
Secure network cables using nylon straps in the appropriate location. Secure cables so that they are not loose or
hanging.
2.
Install battery cables in accordance with paragraph 2-27.
3.
Install wiring gages, switches, and indicators in accordance with paragraph 2-28.
4.
Install junction boxes in accordance with paragraph 2-32.
5.
Install conduit layout in accordance with paragraph 2-31.
6.
Install field instrument layout in accordance with paragraph 2-30.
2-119