TM 10-4320-344-24
h.
Remove five screws (29) .
i .
Remove outlet frame assembly (11) from bulk head panel assembly (3)
2.12.5.3 Inspection.
a .
Inspect bulk head panel assembly (3) and outlet scoop (28) for deterioration
or damage of insulation material on inner surface, corrosion, bends, or
cracks.
b .
Inspect outlet frame assembly (11), exhaust cover links (15 and 18), and hinge
(30) for damage.
2.12.5.4 Repair.
a .
Replace damaged or deteriorated insulation material on inner surface of bulk
head panel assembly (3) and outlet scoop (28).
Refer to Appendix D to
manufacture new insulation material.
b .
Replace bulk head panel assembly (3) or outlet frame assembly (11) if corroded
or damaged to the extent that they can not be properly, mounted or secured.
2.12.5.5 Assembly.
a.
Install outlet frame assembly (11) on bulk head panel assembly (3) and secure
with five screws (29).
b.
Secure handle (27) to outlet scoop (28) with two flat washers (26),
b o l t s ( 2 5 ), flat washers (24), and nuts (23).
c .
Insert screw (20), flat washer (21), linkage bracket (22), and nut (19) on
outlet scoop (28).
d .
Install exhaust cover link (18) on linkage bracket (22) with flat washer (17)
and nut (16).
e .
Install exhaust cover link (15) on exhaust cover link (18) and secure with
screw (14), flat washer (13), and nut (12).
f .
Position outlet scoop assembly (10) in outlet frame assembly (11) and secure
with five screws (9) and nuts (8) with outlet scoop assembly (10) pulled out.
Install two flange bearings (7), flat washers (6), and screws (5).
2.12.5.6 Installation.
Two people are required to lift the bulk head panel assembly onto the pumping
assembly.
Failure to obey this warning may result in personal injury or
damage to the equipment.
a.
Position bulk head panel assembly (3) on pumping assembly (4).
Ensure screw and nut combinations are installed at locations marked during
removal.
b.
Install screws (1) and nuts (2), at locations marked during removal.
2-57