TM 10-4320-309-14
TM 4320-14/1
3-9. CHECKING UNPACKED EQUIPMENT
a.
Inspect the equipment for damage incurred during shipment. If the equipment has been damaged, re-
port the damage on DD Form 6, Packaging Improvement Report.
b.
Check the equipment against the packing slip to see if the shipment is complete. Report all discrepan-
cies in accordance with the instructions of DA PAM 738-750.
c.
Check to see if the equipment has been modified.
3-10. INSTALLATION INSTRUCTIONS
a.
Installation Before Use
NOTE
The discharge and suction extensions are shipped loose and need to be
installed before operating the pump.
(1) Items that require installation before the pump is ready for operation are listed in Appendix C,
Section II, Components of End Item (COEI).
NOTE: Sound enclosure not shown for clarity
Figure 3-3. Pump Setup
35