TM 10-4320-307-24
2-9
UNLOADING-EQUIPMENT BY CRANE (CONT).
a.
Remove shipping tiedowns.
b.
Attach lifting bail assembly to skid.
(1)
Enter wood crate through access end (which is marked) door (1) and remove lifting bail assembly from
storage position.
(2)
Attach four wires (2) to lifting eyes of skid (3) with four shackles (4).
(3)
Assemble two spreader bars (5) on wires (2).
(4)
Attach spreader bars to wire at marking; tighten nuts (6) on spreader bar so spreader bar does not slide
up and down on wire.
(5)
Attach two shackles (7) to each small ring of the 20 top triple ring (8).
(6)
Secure each shackle to a wire (9).
c.
Hoist pumping assembly to its operational site.
2-6